2011
      
      
        LW „BOGDANKA” S.A.
      
      
        
          13
        
      
      
        03.1987
      
      
        Shaft. 2.2 reachesits target depth of 1 018 m.
      
      
        04.1987
      
      
        Concrete cork was made at the bottom of shaft 2.2 therefore final-
      
      
        izing its construction.
      
      
        02.1988
      
      
        Ministry Council resolution no. 34/88 concerning cessation of con-
      
      
        struction of K-2 mine in Stefanow. Shaft 2.1 reached the depth of 
      
      
        the main level at 990 m at the moment of construction hold-up.
      
      
        02.1989
      
      
        Shafts in Stefanow were flooded after water broke into a heading 
      
      
        combining the shafts at the depth of 540 m.
      
      
        11.1989
      
      
        insulation and protection works were finished in shafts 2.1 and 
      
      
        2.2 and the shafts were technologically flooded.
      
      
        03.1993
      
      
        Estates of the liquidated K-2 mine in Stefanow were transferred to 
      
      
        Coal Mine „Bogdanka”.
      
      
        02.1997
      
      
        Development of a document called „The programme for the mine 
      
      
        functioning during the period 1997-2006” which assumed reach-
      
      
        ing gross production capability of 36000 tonnes/day through the 
      
      
        use of the shafts in Stefanow.
      
      
        11.1999
      
      
        The Board’s decision to acitvize the shafts in Stefanow through 
      
      
        the construction of a third field in „Bogdanka” mine.
      
      
        05.2000
      
      
        An agreement with Jastrzębska SpółkaWęglowa S.A. - „Morcinek” 
      
      
        mine to acquire a hoisting machine, a shaft tower and an emer-
      
      
        gency hoist for Stefanow field.
      
      
        10.2000
      
      
        Southern heading driven in seam 385/2 – opening the possibil-
      
      
        ity to start underground mining works towards the shafts in Ste-
      
      
        fanow.
      
      
        11.2000
      
      
        Beginning of driving mining excavations at the main level 990 m 
      
      
        in Stefanow.
      
      
        10.2001
      
      
        Beginning of earth works at the construction of hoisting machine 
      
      
        building at shaft 2.2.
      
      
        09.2004
      
      
        finalizing the tender procedurę for the construction works in Ste-
      
      
        fanow. A consortium was formed by Shaft Constrution Company 
      
      
        (PBSz) from Bytom and Specialized Works Company “East” 
      
      
        (PRS) from Lublin.
      
      
        09.2004
      
      
        Beginning of works in shaft 2.2 to drain and clear the shaft after 
      
      
        15 years since its flooding.
      
      
        01.2005
      
      
        Performing draining hole from 990 m level and beginning of shaft 
      
      
        2.2 drainage. Subsequent clearing of the shaft.
      
      
        07.2005
      
      
        Finalizing the clearing of shaft 2.2 in Stefanow and reaching its 
      
      
        bottom by the teams from PBSz and PRS „East”.
      
      
        09.2005
      
      
        Shaft 2.2 is connected with shaft bottom excavation sat the main-
      
      
        level 990 m.
      
      
        01.2006
      
      
        Beginning of final reinforcements in shaft 2.2.
      
      
        03.2006
      
      
        Beginning of works in shaft 2.1 in Stefanow to clear it and con-
      
      
        tinue its construction.
      
      
        The Board develops and accepts „Strategy of Lubelski Węgiel 
      
      
        „Bogdanka” S.A. development in the period 2006-2014 basing 
      
      
        on the development of Stefanow Field”.
      
      
        06.2006
      
      
        The „Strategy” accepted by Company’s Board of Surervisors.
      
      
        10.2006
      
      
        Finalizing tender procedurę for works in shaft 2.1 in Stefanow. 
      
      
        Signing agreement with the consortium created by PBSz in By-
      
      
        tom and PRS „East” in Lublin.
      
      
        Calendar of the most important events 
      
      
        in 35-year history of „Bogdanka” mine